- Client: Cushman & Wakefield
- General Contractor: Schuchart
- Location: Boise, Idaho
- Building Type: Commercial (Single-Story Bank)
- Size: 5,000 sq. ft.
- Fabrication Site: St. Peters, MO
- Construction Timeline: 2 months fabrication + 4-day on-site install
- Time Saved: Approx. 10 weeks
- Estimated Cost Savings: $100,000 (anticipated)
- Man Hours Saved: Approx. 400
In Boise’s harsh winter conditions, speed was critical. The sooner the NER (electrical) room is operational, the faster the bank could open its doors. With a pressing need to beat the weather and stay on schedule, the project team turned to prefabrication for a faster, more efficient solution.
Why Prefabrication?
- Speed to market
- Cost savings
- Minimized site congestion
- Weather mitigation
- Material waste reduction
Prefabricated Elements:
- 1 fully wired & plumbed NER Room Pod
- 2 complete Bathroom Pods
- 30 exterior wall panels with multi-finish façade (ACM, metal siding, stucco)
Design Process:
- VDC (Virtual Design & Construction) enabled full 3D modeling
- BIM-driven coordination for architecture, MEP, and logistics
- Digitally-generated Bill of Materials (BoM) reduced material waste to near zero
Off-Site Manufacturing:
- Prefab components built in a controlled environment in St. Peters, MO
- Transported via truck & trailer to Boise
On-Site Installation:
- All prefabricated elements installed in just 4 days
- Minimal equipment used (mobile crane, scissor lift)
- Exterior wall panels installed in tilt-up style - eliminated need for long-term scaffolding
Time Saved:
- 2 weeks saved through prefabrication
- Additional 2 weeks saved via pod installation (NER & bathrooms)
- Total timeline reduction of 10 weeks compared to conventional methods
No Delays:
- Installation went according to plan
- Eliminated weather-related delays on the exterior
- Labor Efficiency: Reduced need for on-site crews
- Waste Reduction: Near-zero material waste
- Back-End Cost Savings: Accelerated schedule saved overhead costs
- Estimated Savings: $100,000 (preliminary estimate)
Key Challenges:
- Precise tolerances required by the National Financial Institution
- Complex MEP coordination
- Schedule logistics
- Transportation constraints
Solutions:
- Extensive pre-planning & digital QA/QC documentation
- CNC milled drywall and plywood enabled accurate electrical box placement
- Deviation reports ensured layout precision post-steel erection
- Reduced On-Site Impact
- Zero Material Waste (via BoM-driven procurement)
- Enhanced Quality Control: Fabrication in controlled setting with documented QA/QC processes
- Energy Efficient Construction Process
Project Wins:
- Entire exterior and pod installation completed in 4 days
- Avoided winter weather delays
- Accelerated project turnover
- Set a benchmark for future National Financial Institution prefab builds
Key Takeaway:
Prefabrication enabled rapid construction with zero compromise on quality, all while navigating weather risks, tight tolerances, and high-performance standards. The collaboration and digital tools ensured that this project was not only faster—but smarter.